Gaining planning permission for Oaklands Solar Farm

With a capacity of 138 MW of solar power and up to 37.5 MW of battery energy storage, Oaklands Solar Farm is a significant contributor to the UK’s decarbonisation.
Solar farm

Project facts

  • Client
    BayWa r.e. UK Ltd.
  • Location
    South Derbyshire, UK
  • Date
    2021 - 2024
  • Challenge
    Ensure that solar farm traffic didn’t have an unacceptable impact on the community.
  • Solution
    Proper assessment and development of access strategies ensures that the community will be protected.

The challenge

Oaklands Solar Farm will cover around 400 acres, crossing public roads and requiring access close to sensitive villages and along rural lanes. As a Nationally Significant Infrastructure Project, an extensive environmental impact assessment was required to accompany an application for a Development Consent Order.

Determined by the Secretary of State, our work has been closely scrutinised through a planning inquiry. 

The solution

We worked closely with the project team over several years to develop a robust assessment and presentation of our case at inquiry.

This included:
Significant stakeholder engagement
Consideration of multiple scenarios to respond to changing context
Working to defined timescales through the planning inquiry
Engineering design drawings to confirm swept paths of larger vehicles including abnormal loads
Production of a Traffic and Transport EIA chapter
Development of a robust Construction Traffic Management Plan

Our assessment drew on best practice guidance published by the Project Director, Andy Ross, through his work with the Institute for Environmental Management and Assessment.

Mark Lever Green

Bringing our industry-leading knowledge of environmental assessments, we have presented a robust case for a new solar farm to support the development of clean electricity and protect the local community during its construction.

Mark Lever-GreenAssociate, Sustainable Development

The result

By presenting a robust case and working with the client and wider project team collaboratively, we went into the Public Inquiry with most issues resolved and secured through statements of common ground with key parties. 

The Development Consent Order was granted in 2025 with construction following shortly after. The mitigation that we have secured through our work will continue to ensure that the impact on local communities through construction and beyond is minimised.

Our experts  are happy to assist you - Experts team Sustainable development

Our experts are happy to assist you

Experts team Sustainable development

Sustainable development

Discover our vision-led approach to planning new communities to embed sustainable commuting from the outset.

 

Read more
City model